KHD installs Pyrorotor Calciner Technology for highly flexible alternative fuel burning in Austria

Cologne-based Humboldt Wedag GmbH has been awarded an EPC contract by Rohrdorfer Cement Group for the kiln line modernization at its cement plant operations in Gmunden/Austria. The kiln modification will enable the very flexible usage of a wide range of waste fractionally pre-treated derived fuels on a high substitution rate.

The modernization project comprises the design and supply of KHD’s world´s first ever Pyrorotor Calciner Technology as well as the replacement of the existing satellite cooler with a new generation Pyrofloor PFC2 clinker cooler. The existing three station rotary kiln will be fitted with a new kiln drive and a new kiln hood as well as kiln inlet and outlet.

With the installation of the new Pyrorotor Calciner Technology from KHD the Gmunden plant will be able to burn very coarse waste-derived fuels including whole rubber tires, which will lead to drastically reduced requirements in regard to waste pre-treatment. Therefore, the kiln modification will also emphasize pollutant emission reduction.

New KHD technology core components are:

three new preheater cyclones

new preheater ID-fan

Tertiary air duct

Pyrotop compact calciner mixing chamber

Pyrorotor calciner burning chamber technology

Pyroclon calciner burning system

new kiln bypass unit

multi-fuel Pyro-Jet kiln burner for primary and secondary fuels

new kiln drive and kiln hood

Pyrofloor PFC2 clinker cooler equipped with a Pyrocrusher roller type clinker crusher

Simulex plant simulation software

KHD services include the dismantling of existing equipment parts as well as the engineering, design, supply and erection of new equipment incl. commissioning services. Commissioning of the new system is scheduled for April 2019.

www.khd.com

Related articles:

11/2010

New 4000 t/d clinker production line for Syria

GÜRIS Insaat ve Mühendislik, Turkey awarded Humboldt Wedag/Germany a contract to provide a new pyroprocess system with a capacity designed for 4000 t/d clinker. GÜRIS already operates two cement...

more

New 4000 t/d clinker production line for Syria

GÜRIS Insaat ve Mühendislik, Turkey awarded Humboldt Wedag/Germany a contract to provide a new pyroprocess system with a capacity designed for 4000 t/d clinker. GÜRIS already operates two cement...

more
4/2016 US 2016/0046525 A1

Plant for producing cement clinker with gasification reactor for difficult fuels

(22) 04.04.2014 (43) 18.02.2016 (57) A plant for producing cement clinker, comprising as viewed in the direction of materials flow, a heat exchanger to preheat raw meal, a downstream calciner to...

more
4/2016 US 2016/0039714 A1

Method for operating a plant for producing cement

(22) 04.04.2014 (43) 11.02.2016 (57) A method for operating a plant for producing cement clinker from raw meal having, as viewed in the materials flow direc­tion, at least one calciner for...

more
01/2013

Holcim orders 9000 t/d cement plant at KHD

KHD Humboldt Wedag International AG subsidiaries, Humboldt Wedag India, Pvt. Ltd. and Humboldt Wedag GmbH (collectively “KHD”) received an order from the Holcim Group company ACC Limited, India, for...

more