New shell section for the rotary kiln

The heart of the Leube cement plant is its rotary kiln. For the 2016/2017 winter repair scheme, Leube invested some € 200 000 in a new shell section. “Our kiln’s rotating tube is 45 m long and therefore cannot be transported in one piece. Consequently, it arrives in individual parts called sections, which are then welded together on site”, explains Engineering Division Chief Günter Waldl.

The maintenance team was able to remove, overhaul and reinstall the most important component of all, the so-called tire bore from the plant’s old rotary kiln (out of service since 2010). This entailed extracting the 2.5 cm-thick steel section from the old kiln with a cutting torch and lifting it away with a heavy duty crane. The tire bore is 2 m long, has an inside diameter of 3.6 m and a wall thickness of 5 cm.

 

Components fitted together by crane

A crane was used to raise the overhauled parts and properly align them for dead-on fixation in the rotary kiln. “The kiln has to be axially positioned to millimeter accuracy”, explains Maintenance Chief Christian Wörgötter, “or its rotary motion afterwards will be wobbly”. Then, the tube was rewelded at the interfaces. “Such work has to be done by hand. We had to do the welding in several layers, each time inspecting the last pass for cracks in order to perform any necessary rectifications on the spot”, says Wörgötter. Each interface required welds with a length of about 11.3 m. All in all, the work took seven weeks to complete.

 

“That was challenging work”

“The lifting and fitting together of components that weigh 32 t each”, reports Wörgötter, “was especially difficult in the limited space around the rotary kiln. It was also very challenging for the people from Kremsmüller Industrieanlagenbau to get the spare parts properly aligned.

The old shell section stems from the cement plant’s first rotary kiln, which was initially installed in the 1960s. Delivery of the parts was a spectacular affair: They did not arrive by flatbed truck as usual, but were instead pulled by sled over snow-covered roads and highways from the Salzburg train station to St. Leonhard. At the time of its extraction in December 2016, the shell had accumulated some 350 000 operating hours. All that time, Leube had been monitoring its wear state, ultimately determining that it had reached the end of its service life. “We decided to replace it quickly in order to avoid component failure and a resultant prolonged period of kiln outage”, explains Waldl.

www.leube.at

Related articles:

5/2018 WO 2018/042401 A1

System and method for aligning kiln shell sections

(22) 05.09.2017 (43) 08.03.2018 (57) A system for radially and axially aligning a new kiln shell section with an existing kiln shell section during a kiln shell section replacement or kiln erection...

more
10/2017 LEUBE KALKWERK

Comprehensive refurbishment of a multichamber shaft kiln

The multichamber shaft kiln at Leube Kalkwerk limeworks in Golling/Austria, is an extremely hard worker: Since its installation in 1989, it has been producing 200 t of burnt lime – that’s eight...

more
10/2017 PL1957423 (T3)

Method and apparatus for treating lime mud

(22) 21.11.2006 (43) 30.06.2017 (57) Summary of corresponding patent WO2007057512 (A2): A method for feeding lime mud into a lime kiln including a rotary kiln shell having an interior between a first...

more
05/2012

One of the cleanest cement plants in the world

A new EMC baghouse (EMC – Energy Minimizing Concept) was installed in the Leube cement factory for about 5 million € to dedust the kiln exit gases. With the new filter, the project target value of...

more

One of the cleanest cement plants in the world

A new EMC baghouse (EMC – Energy Minimizing Concept) was installed in the Leube cement factory for about 5 million € to dedust the kiln exit gases. With the new filter, the project target value of...

more