MAERZ OFENBAU AG

Maerz Ofenbau projects in Mexico and Russia

A third kiln for the lime plant Mexicana de Cobre/Mexico

Not far away from the Sonora desert, in the same-named federal state of Mexico, two Maerz kilns erected in 2009 and 2014 are performing to the complete satisfaction of their owner Mexicana de Cobre. In 2019 the customer demonstrated its confidence in Maerz technology by ordering a third Maerz kiln for its lime plant.

Near the town Agua Prieta on a picturesque plateau more than 1300 m a.s.l., the customer’s engineers are preparing the ground for the new kiln of the circular R4S type, which will process limestone with a grading of 60-110 mm and will produce 600 t of burnt lime per day.

This kiln project marks an important milestone for Mexicana de Cobre enabling it to cope with the increasing demand for lime in its mining business. The customer is the fourth largest copper producer worldwide.

The order includes the supply of engineering, license, know-how, equipment as well as technical assistance ser-vices during erection, commissioning and start-up of the Maerz PFR lime shaft kiln at the customer’s lime plant. Natural gas will be used as fuel. Maerz’s equipment supply comprises the following main items:

Suspended cylinders

Process air blowers with electric motors

Electric, measuring and control system for the lime kiln

Firing system for natural gas, including the start-up burner equipment

Hydraulic equipment

Limestone skip hoist winch, including the pertinent electrical measuring and control equipment

Air blast units

Refractory materials

 Maerz’s specialised technicians will assist with hot commissioning and acceptance test runs on the lime kiln and the associated equipment.

Abinsk Electric Steel Works Ltd, Abinsk, Krasnodar Region, Russia

Abinsk Electric Steel Works Ltd., domiciled in Abinsk, Krasnodar Region, Russia, placed an order for the supply of engineering, license, know-how, equipment and technical assistance services during commissioning and start-up of a Maerz PFR lime shaft kiln as well as the limestone and lime handling systems designed by Parget Makina Ltd., based in Ankara/Turkey.

This new double shaft lime kiln of the rectangular type E2 will calcine limestone with gradings of 20-40 mm and 55-100 mm respectively and will produce more than 160 tons of lime per day, using natural gas as fuel. Commissioning is scheduled for the middle of 2020.

The supply of this new lime plant is a cooperation between the companies Parget Makina Ltd. from Ankara/Turkey and Maerz Ofenbau AG.

www.maerz.com

x

Related articles:

Issue 2012-02

Second lime kiln for Karadeniz

Karadeniz Madencilik San. ve Tic. Ltd. S¸ti., domiciled in Istan­bul, Turkey, placed an order with Maerz for the supply of engineering, license, know-how and equipment as well as technical...

more
Issue 2012-07

Finelime kiln for Mexico

Minorte S.A. de C.V, domiciled in Monterrey (Nuevo León), Mexico, and a member of ­Calidra Group, entrusted Maerz with the supply of engineering services, license, know-how, materials and equipment...

more
Issue 2019-12 MAERZ OFENBAU AG

Recent projects by Maerz Ofenbau

Gangyuan Co. Doo, Smederevo/Serbia, placed an order with Maerz Ofenbau AG for the supply of engineering, license, know-how, equipment as well as technical assistance services during erection,...

more
Issue 2012-01

Lime kiln for Thailand

The Golden Lime Co. Ltd. from Bangkok/Thailand, is going to install a Maerz Lime Kiln No. 5, a 150 t/d coal/petcoke dust fired unit, at their Lopburi Plant and has signed a corresponding contract with...

more
MAERZ OFENBAU AG

A single shaft Maerz HPS kiln for Schaefer Kalk Malaysia

Schaefer Kalk GmbH & Co. KG, the renowned German lime manufacturer, has been operating a major lime plant in Kuala Ketil, a small town in North Malaysia’s Kedah province since 1997. As is typical for...

more