After two years of intense work, the first clinker was received on schedule at HeidelbergCement’s Burglengenfeld cement works in Germany in April 2018.

IKN was awarded a contract for engineering, supply and installation to upgrade the pyro line to 4000 t/d – from raw meal feeding to clinker discharge. The contract included integration engineering, supply and installation of add-on components for the raw meal grinding plant. The upgraded kiln line features state-of-the-art technology in order to reach the targeted production level and to comply with future emission limits. The new production line comprises a two-string, 5-stage preheater tower with inline calciner and Fire Bed Combustor for coarse RDF. IKN’s most modern preheater and calciner design ensures minimum pressure drop at maximum performance and high efficiency. The kiln line has been designed for maximum use of a broad range of alternative fuels.

With the upgrading of one of Europe’s most modern clinker lines, IKN is proud to have been selected as trusted partner for this enormously challenging project on EPC basis.

//www.ikn.eu" target="_blank" >www.ikn.eu:www.ikn.eu

x

Related articles:

IKN GMBH

New kiln line at Burglengenfeld plant, Germany started production

After two years of intense work, the first clinker was received on schedule at HeidelbergCement’s Burglengenfeld cement works in Germany in April 2018. IKN was awarded a contract for engineering,...

more
Issue 1-2/2016 IKN GMBH

IKN wins contract for a pyro line in Germany

In August 2015, IKN was awarded the contract for the engineering, supply and installation of a complete 4000 t/d pyro line – from raw meal feeding to clinker discharge – at Burglengenfeld/Germany....

more
Issue 6/2016 THYSSENKRUPP INDUSTRIAL SOLUTIONS AG

thyssenkrupp to supply new cement clinker production line to HeidelbergCement

thyssenkrupp Industrial Solutions has received a contract from Heidelberg­Cement AG to supply a new cement clinker production line. The 4500 t/d facility will be built at the Schelklingen plant in...

more
Issue 6/2016 A TEC GRECO

IKN placed order for A TEC Greco Kiln Burner

A TEC Greco will deliver its Kiln Burner to HeidelbergCement’s plant at Burg­lengenfeld/Germany. The project will be realized by the end of 2016 and is part of a complete modernization of the plant...

more
Issue 03/2014

Kiln rehabilitation in Tanzania

1 Introduction In spring 2011, the Intercem Group with offices in Zurich/Switzerland and Oelde/Germany received the contract to modernize the cement plant Wazo Hill of the Tanzania Portland Cement...

more