ROHRDORFER

Rohrdorfer is first cement plant in Germany to build CO2 separation plant

Germany’s first CO2 separation plant for cement production is currently being built on the premises of the Rohrdorf cement plant. The pilot project is a milestone for a climate-neutral cement production. Two tons of CO2 are captured per day and converted into raw material for the regional chemical industry.

Rohrdorfer, the operator of the cement plant, is launching the pilot project on its own initiative in order to explore the possibilities of carbon dioxide capture and thus climate-friendly cement production. The plant, which is being built in cooperation with the Andritz Group, is scheduled to start up by the end of June 2022. It will capture 2 t of carbon dioxide per day, which will be put to further use in the regional chemical industry in the spirit of the circular economy. The total cost of the pilot plant is € 3 million and will be borne by Rohrdorfer.

The foundation for the plant on the south side of the Rohrdorfer cement works is already in place.The pilot plant will test the technical, qualitative and economic conditions for CO2 capture and conversion. Up to now, only empirical data from capture plants used in coal-fired power generation have been available.

Production of formic acid for the chemical industry starting in fall 2022

For the Rohrdorf cement plant, the Andritz Group has customized the plant so that, as a result, the optimum purity of the CO2 can be achieved while at the same time ensuring a high longevity of the chemical solvent used for separation.

Once the CO2 capture process has been sufficiently tested, Rohrdorf engineers and designers will expand the plant to produce formic acid, a versatile chemical, from the captured carbon dioxide. This is expected to be possible in the fall of 2022. Rohrdorfer has already been testing the extraction of formic acid from carbon dioxide in the company’s own laboratory since July 2021 in order to be optimally equipped for production in the pilot plant. Around 1800 l of formic acid can be obtained from the 2 t of CO2 captured per day in the plant. This is supplied to chemical plants in the region, for example, and serves as the basis for products such as cleaning agents, disinfectants or deicing agents. Depending on the degree of purity, the CO2 obtained can also be used in the food industry, for example for carbonic acid enrichment of mineral water.

CO2 as a carbon source important for the energy turnaround

The results of the pilot project are an important step for Rohrdorfer in achieving the German cement industry’s goal of producing climate-neutral cement by 2050. As early as 2022, cement will be produced at the Rohrdorf site with 45 % less CO2 than in 1990. This will be achieved by optimizing cement types and fuel use. By 2030, a reduction of 65 % is to be achieved. The remaining 35 % can only be reduced by capture. The pilot plant for CO2 capture is intended to accelerate this development.

Carbon dioxide capture is also an important contribution to the energy transition: Through the sector coupling of the chemical industry and the cement industry, the captured and converted carbon is to replace crude oil and natural gas in the chemical industry in the medium term. This is the start of a CO2 circular economy.

“We need to start seeing carbon dioxide as a valuable material instead of a problem material. The carbon in CO2 can become methanol, ethylene or formic acid, and thus a starting material for many products that today still have to be produced on the basis of petroleum. With this pilot project, Rohrdorfer is about to become a reliable partner for the chemical industry, for example at the chemical sites in Burghausen or Linz,” says Dr. Helmut Leibinger, Head of Plant and Process Engineering at Rohrdorfer. “With CO2 as a carbon source, Germany can protect the climate and at the same time become less dependent on oil and natural gas. In addition, value creation and thus jobs remain in the country.”

On 25 January 2022, Prof. Dr. Angelika Niebler, Member of the European Parliament and Deputy Party Chair of the CSU Bavaria, together with the Rohrdorfer management broke ground for the plant. Ms. Niebler welcomed Rohrdorfer’s initiative to proactively drive forward the production of CO2-neutral cement: “In order to achieve the goals agreed at the climate conference in Paris, determination and initiative are required. Rohrdorfer’s pilot project is outstanding and shows that German industry is ready to take responsibility.”

www.rohrdorfer.eu

Fact Sheet Rohrdorfer
Year of foundation: 1930
Five divisions: cement, ready-mix concrete, sand and gravel, precast elements, concrete products
Employees: 2130 in Germany, Austria, Italy and Hungary
Locations/plants: 142
Companies: 30
Total investment in plant modernization for environmentally friendly production: € 175 million (since 2006)
Results CO2 reduction: As early as 2022, cement will be produced at the Rohrdorf site with 45 % less CO2 than in 1990
CO2 reduction targets: A reduction of 65 % is to be achieved by 2030, and climate-neutral production by 2050
More information: www.rohrdorfer.eu
Sustainability at Rohrdorfer: www.rohrdorfer.eu/nachhaltigkeit
x

Related articles:

Issue 6/2022 ONESTONE CONSULTING LTD.

Next-generation carbon capture technologies for cement industries

1 Introduction According to the International Energy Agency (IEA), we are approaching a decisive moment for international efforts to tackle the climate crisis. In its ‘Net Zero by 2050 Scenario’...

more
Issue 11/2019 DALMIA CEMENT (BHARAT) LIMITED

Dalmia Cement (Bharat) Limited and Carbon Clean Solutions team up to build one of the cement industry’s largest carbon capture plant

Dalmia Cement (Bharat) Limited, a leading Indian cement major and a subsidiary of Dalmia Bharat Limited, has announced that it will build a large scale facility of 500000 t/a carbon capture at its...

more
Issue 3/2023 HEIDELBERG MATERIALS

CO2 as raw material: Heidelberg Materials and Linde build one of the world’s first large-scale CCU facilities in a cement plant

Heidelberg Materials and Linde have established a joint venture under the name “Capture-to-Use” (CAP2U) to build and operate a state-of-the-art carbon dioxide capture and liquefaction plant. One of...

more
Issue 3/2021 HEIDELBERGCEMENT AG

HeidelbergCement pioneers new carbon capture technology in Redding/USA

HeidelbergCement’s US subsidiary Lehigh Hanson and Silicon Valley-based materials technology company Fortera have announced a collaboration to implement a new type of carbon capture and utilisation...

more
Issue 7-8/2020 AKER SOLUTIONS

Aker Solutions‘ carbon capture and storage technology gets DNV GL approval

Aker Solutions’ technology for a full-scale demonstration project in Norway to remove carbon emissions at a cement plant has been approved as qualified by DNV GL, the technical advisor to the oil and...

more