Latest EPC kiln line upgrade project for Duna Drava Cement in Vác/Hungary
The 2400 t/d Duna Drava Cement clinker line in Vác was successfully re-commissioned and put into production in April 2018.
In less than two years, IKN completed the enormous task of delivering the project on EPC basis.
The main target of the project was to adapt the pyro line for producing clinker using up to 100 % RDF in the calciner. The two lower cyclone stages were replaced, a complete new preheater tower with the inline calciner was erected, a new bypass system as well as a new static inlet in the clinker cooler were installed.
The upgraded kiln line combines
the latest industry practices with the most modern and up-to-date process technology.